Frame Inspection..

22.04.2010

Engaged an independent building surveyor to inspect the Frame (and Slab)..
We were asked to come on 22/April
(I was told the frame would be finished by that time).

We reached on time on the 22/April..
The trades people are still working on Frame Trusses..
The scaffolding people are working on the site too..

Met the Site Supervisor and Construction Manager for the first time..

One big SHOCKER !!

The front porch slab has been built too short and out of square, and will need to be extended.
How can they do such goof-ups??

The builder says it is the responsibility of the contractor to measure the slab (
WTF)

Anyways lets see how do they fix the issues
Hoping it can be rectified and they will get this fixed.

The frame inspection done, and the report submitted to the Construction Manager and Site Supervisor.
They will review and provide their response next week.

Some pictures from the Frame Inspection day

The House:




Looking in from the entry door:


The Lounge (as seen from the family room):



The Study:


Main Bedroom:


The view from the window of my son's bedroom :)
Lake Caroline: (zoomed 8x)


The actual lake:


View of our house from Lake Caroline: (zoomed 8x)



Kitchen:


Bullet marks:


Workmanship ;)


Main Bathroom:


Rumpus Room:



1 comment: